East Norwalk Train Station

Project Update

Two Weekend Closures Planned in June at East Norwalk Train Station

The East Norwalk Train Station will be temporarily closed for two weekends in June 2025. The first closure will occur from Saturday, June 21 - Sunday, June 22, re-opening for first trains Monday, June 23, and the second closure is scheduled for Saturday, June 28 - Sunday, June 29, re-opening for first trains Monday, June 30.  These closures are necessary to facilitate construction activities, including work on temporary platform access ramps. Normal train service will resume after each weekend closure.

The East Norwalk Train Station is currently undergoing improvements to the station, platforms, and parking areas. Once completed, the station will feature two new platforms that can accommodate six train cars, new platform canopies, and enhanced parking and access options, including a dedicated drop-off lane. The improvements to the East Norwalk Train Station are expected to be completed by 2027. 

EAST NORWALK TRAIN STATION INFO

Please be advised that there will be no train service in either direction, and parking will be unavailable on the north side of the train station during the closure weekends. The first closure is from Saturday, June 21 - Sunday, June 22, re-opening for first trains on Monday, June 23, and the second closure is from Saturday, June 28 - Sunday, June 29, re-opening for first trains on Monday, June 30. We encourage you to plan your travel accordingly during these weekends.

EAST NORWALK TRAIN STATION IMPROVEMENTS

The East Norwalk Train Station will be updated as part of the Connecticut Department of Transportation’s (CTDOT) Track Improvement Mobility Enhancement (TIME) 2 Projects - a sub-component of the WALK Bridge Replacement project.

The Train Station upgrades include extending platforms on both sides of the station to accommodate six train cars, new platform canopies, and improved parking and access - including a dedicated drop-off lane.

Construction began in March 2024 and will take approximately four years. During this time, four separate (3-week-long) temporary train station closures will occur at the station.

Please sign up for project alerts here

 

At a Glance

Anticipated Construction Start: March 2024

Construction Duration: 4 Years

(Timeline is phased with work beginning on the station's north side and then on the south side of the station).

Highlights

Platform extensions on both sides to accommodate six train cars

New platform canopies

Parking lot Improvements 

ADA accessibility

New dedicated drop-off lane